Design related BRTS - Update


Sabir Khan Sadozai, the project director for the Muslim Town flyover, said that the repair of the service roads had initially been delayed because the Water and Sanitation Agency had to lay a sewage line. Then the Traffic Engineering and Transport Planning Agency (TEPA) stopped the repairs as the final design of the elevated bus lane for the Metro Bus Service, being drawn up by the National Engineering Services of Pakistan (NESPAK), had not arrived. “Otherwise we could have had a situation where we finished the reconstruction of the road but TEPA had to break sections of it again to lay piers for the elevated bus lane,” he said.
Sadozai said that the design of the bus lane had been received from NESPAK last week and they had started the road works. He said that WASA still had some work to finish, namely to raise the height of gutter necks on Wahdat Road and Ferozepur Road so that the manholes were at the same level as the road. He said that work on the service lane around FC College and the 1122 office would be finished in a few days. He said some sections of the road would not be repaired until after the bus lane is finished.
Asked why the design of the bus lane for the MBS project had been changed and delayed, TEPA Director Mazhar Hussain, who is in charge of the construction, said that the decision had been made to avoid the expense and hassle of having to acquire land for a ground-level bus lane.

No comments:

Free Blog Counter